On February 27th, a tragic accident occurred at Itaquerao Stadium, a newly constructed venue for the Corinthians football club in Sao Paulo, Brazil. A tower crane collapsed while lifting a metal component, causing significant damage to parts of the stadium's stands and resulting in the deaths of three individuals on the spot. The exact cause of the incident is still under investigation, but authorities have already called for an immediate technical review to prevent similar incidents from happening again.
The stadium, which is set to host matches during the 2014 FIFA World Cup, was reported to be 94% complete at the time of the accident. The first match was scheduled for January 5, 2014, but the incident has raised concerns about potential delays. Despite the accident, Brazilian officials have stated that the opening ceremony and the first game of the World Cup will not be affected.
Lopez, head of the fire department, confirmed that the falling metal parts damaged parts of the stands and that three people lost their lives. He emphasized the need for engineers to conduct a thorough inspection of the site as soon as possible. Witnesses reported that the crane was lifting 500 tons of metal ceiling components when the accident occurred, leading to the destruction of part of the east stand and the two-story structure above it.
Odebrecht, the company responsible for the stadium's construction, has yet to provide an official explanation for the collapse. However, FIFA Secretary General Jerome Valcke confirmed that the opening match would still take place at the stadium, despite the incident.
In response to the accident, the Brazilian World Cup Organizing Committee, along with the construction and design teams, held an emergency meeting. They acknowledged that the stadium’s completion date might be delayed by two months, but they remain confident that the opening ceremony and the first match will proceed as planned.
The Coutinho Group, which designed the stadium, stated that the reconstruction work would involve replacing a large LED screen and a 420-ton steel frame. Engineer Barbosa from Coutinho assured the public that the internal structure of the stadium remained intact, and there was no risk of the entire building collapsing.
FIFA also issued a statement confirming that they are waiting for the results of the ongoing investigation before making any changes to the original schedule. For now, the opening game remains unchanged, and the focus is on ensuring the safety of all future operations at the stadium.
Suzhou FUJI Precision Elevator Co.,Ltd , https://www.profuji.com