Raised floor construction technology

1 Clean the floor of the site where the raised floor is to be installed and require the floor to be flat and dry. It should be the ground where the cement mortar is leveled, and the height difference is less than 4 mm with a 2 meter level.

2. Position the cleaned ground wire to determine the position of each bracket.

3 Install the bracket at the fixed position, install the bezel and adjust the height of the entire bracket.

4 Assembling the bracket beam and adjusting the beam level at the same time, it is recommended to use a laser level and then tighten the screws to fix the beam.

5 Install the raised floor while trimming the raised floor.

6 Install the baseboard after the floor is installed to protect and beautify the wall.

7. Clean the floor surface after the construction is completed.